Status
The project is slightly
behind schedule. The team
has approved the Digital
Core Requirements. The team is working on the design
document to show how the design
is going to be implemented and how it will meet
all of the
requirements that have been approved.
The schematics and board layout are
complete for the basic design. Some minor modifications are being
completed to the schematics. Once the modifications are complete the
first
board turn will be ordered.
When the board is being ordered I will
spend my time writing all of the test plans that will
happen for
the second semester of Senior Design.
Last Updated:
03-May-2008
|