CSU IAC Summary of Results - FFY 2000

October 1999 - September 2000


Manufacturers Served 24
Number of Recommendations 192 ARs
Total Recommended Cost Savings $2.82 Million/yr
Total Estimated Implementation Cost $2.33 Million
Average Payback Period 0.83 years
Implementation Rate for Period 50%

 
 
Energy Type  Recommended 
Savings 
Recommended 
Cost Savings 
Electrical Consumption 10,234 MMBtu/yr $66,440 /yr
Electrical Demand 16,534 kW-months/yr $177,430 /yr
Other Electrical Fees N/A $0 /yr
Natural Gas 32,475 MMBtu/yr $125,910 /yr
L.P.G. 0 MMBtu/yr $0 /yr
#1 Fuel Oil 0 MMBtu/yr $0 /yr
#2 Fuel Oil 0 MMBtu/yr $0 /yr
#4 Fuel Oil 0 MMBtu/yr $0 /yr
#6 Fuel Oil 0 MMBtu/yr $0 /yr
Coal 0 MMBtu/yr $0 /yr
Wood 0 MMBtu/yr $0 /yr
Paper 0 MMBtu/yr $0 /yr
Other Gas 0 MMBtu/yr $0 /yr
Other Energy 0 MMBtu/yr $0 /yr
Water Disposal 2,548,960 gallons/yr $2,660 /yr
Other Liquid (nonhaz) 136,570 gallons/yr $77,290 /yr
Other Liquid (haz) 3,389 gallons/yr $3,650 /yr
Solid Waste (nonhaz) 1,121,490 pounds/yr $169,260 /yr
Solid Waste (haz) 159,943 pounds/yr $13,070 /yr
Gaseous Waste 1,160 pounds/yr $0 /yr
Personnel Changes N/A $313,740 /yr
Administrative Costs N/A $17,110 /yr
Primary Raw Material N/A $674,160 /yr
Ancillary Material Cost N/A $438,540 /yr
Water Consumption N/A $2,710 /yr
Primary Product N/A $739,040 /yr
Byproduct Production N/A $0 /yr
TOTALS $2,821,010 /yr